On December 31, 2021, the Shangshui Huji 22.8MW Distributed Wind Power Project achieved full-capacity grid connection.
Shangshui Huji 22.8MW Distributed Wind Power Project is located in Huji Town and Weiji Town, Shangshui County, Zhoukou City, Henan Province, with a planned installed capacity of 22.8MW by 7 (6x3.3MW and 1x3.0MW) wind turbines, supported by a 35KV switch station. The project officially started construction on August 19, 2021, the installation of the last wind turbine was completed on December 29, 2021, and the full-capacity grid connection of the entire wind farm was completed on December 31, 2021.
During the construction period, the Project Department overcame many difficulties such as heavy rainfall in the rainy season, complicated coordination of land acquisition, tight supply of equipment, and repeated covid epidemics. The Project Department insisted on scientific management, orderly organization, and continuous construction around the clock to ensure the full capacity grid connection of the wind farm to be successfully achieved.
At 17:30 on December 30, the 12MW Distributed Wind Power Project in Fengzhen, Guanyunxu, Lianyungang realized full-capacity grid connection.
The project is located in Guanyun County, Lianyungang City, Jiangsu Province. The wind farm is about 5km long from north to south, and about 3km wide from east to west. There is provincial highway S324 on the south side of the site, and high-speed G228 on the east side. In this phase of the wind farm project, four wind turbines with a stand-alone capacity of 3.0MW will be installed.
In the follow-up construction management of the project, all colleagues in the Guanyun Project Department will continue to strengthen strict control over the safety, quality, and progress of on-site construction, unswervingly practice the Company's core values, and ensure the smooth completion of all tasks!