At 11:52 on November 23, with the gradual completion of the docking of the WTG blade and the nacelle, it marked the successful completion of the hoisting of the first WTG of our Shangshui Huji 22.8MW Distributed Wind Power Project.




Shangshui Huji 22.8MW Distributed Wind Power Project is located in Huji Town and Weiji Town, Shangshui County, Zhoukou City, Henan Province, with a planned installed capacity of 22.8MW and 7 (6x3.3MW and 1x3.0MW) wind turbines installed. The project also includes the construction of a 35KV switch station. The first hoisted WTG unit is a Yunda 3.3MW. The center height of the hub is 140 meters (6-section tower), the diameter of the blade is 164 meters, and the heaviest part is the first section of the tower, weighing 113.884 tons.


Transportation of blade


Hoisting of tower section


Hoisting of nacelle


Hoisting of blades and hub


Before hoisting, the Project Department conducted strict calculations based on the parameters of the WTG and the crane, and conducted a comprehensive safety technical disclosure of the WTG installation by the construction team, and implemented the Company's relevant safety management rules and regulations. During the hoisting, the personnel of the Project Department tracked the whole process, kept an eye on the weather changes, monitored the wind force, and notified the on-site personnel in time to provide guarantee for the safe construction of the staff during the hoisting. Since the start of the project, the Project Department has overcome construction problems such as continuous rainstorms, covid epidemics, and poor geological conditions, carefully organized, made overall arrangements, actively coordinated the hoisting team, machinery and equipment to enter the site, and carefully organized the hoisting work, so that the project construction can be achieved steadily, safely, and efficiently and advanced in an orderly manner.



At the construction and installation site, all staff of Shangshui Project Department carried forward the fine tradition of "Green people", unswervingly practiced the Company's core values, marched forward bravely, and won the "year-end battle". The goal of full-capacity grid connection on December 30 was successfully realized.